Construction of Dong Nai Power Company's Operation Control Center (OCC)




Project detail


Project scale:

The system connects more than 25 110kV substations and equipment on the medium voltage grid through IEC 60870-5-101, IEC 60870-5-104 protocols.

The project has been implemented and completed on schedule, and has been in operation since the second quarter of 2016 until now.

In early 2016, My Phuong Trading Company cooperated with Dong Nai Power Company in the project of Building Control Center with software of Survalent/Canada. This is an important step in the comprehensive development of smart grid in Dong Nai province with SCADA/DMS/OMS system.

The requirement set out in the project is to completely replace ABB's SCADA system that was built more than 10 years ago. The Survalent SCADA system will connect all signals from high voltage stations and equipment on the medium voltage grid.