Quy Hop 110KV Substation Project




Project detail

Quy Hop district, Nghe An province

MPCo has participated in supplying 35kV, 5MVAr capacitor banks of Cooper with reactor for this project

The project was completed at 16:00 on June 7, 2014 and combined with the periodic testing of the substation, the capacitor bank was successfully energized and operated at 19:30 on the same day

Following the direction of the Northern Power Corporation in reducing power loss and improving voltage quality, the Northern High Voltage Grid Company implemented a plan to install medium voltage capacitor banks for 110kV substations managed by the Company. Quy Hop 110kV substation is the first 110kV substation to install a 35kV capacitor bank with a 5MVAr capacity.